Purpose
Clark Public Utilities provides water service to over 40,000 homes and businesses in unincorporated Clark County. As a part of our commitment to providing reliable and safe water service to customers living in the Hazel Dell service area now and into the future, the utility has identified a series of system improvement projects to address safety, water capacity availability and to support future population growth in the area.
Benefits
The 4.3-mile stretch of water main running east-west along NW 99th Street, from NW Lakeshore Ave to NE St. Johns Road is ready for an update. The existing water main consists of a combination of different pipe diameters (including 10in, 16in, 24in) and will be updated to a 30in water main across the full length to provide adequate and reliable service for the growing area. You may recall in recent history there have been some disruptive pipe-breaks along this section. The new 30in main line will increase system reliability and help to minimize future disruptions along this 4.3-mile stretch of NW 99th Street.
Timeline & Status Updates
This project is scheduled to happen in three phases to minimize local impacts. Final finish paving for the project is scheduled after all phases of the project are complete.
-
- Work on phase one, which includes the section of NW 99th between NW 4th and NW 11th, started in July, 2024. Phase one was initially completed in August, 2024.
- Work on phase two, which includes the section of NW 99th between NW 21st and NW 29th, started in September, 2024 and was initially completed in December, 2024.
- Work on phase three, which includes the section of NW 99th between NW 9th and NW 21st, started in January, 2025 and is anticipated to be complete in February, 2025.
- Final water line testing and connection to water lines within side streets is scheduled for February 2025 through March 2025.
- Final paving and striping is scheduled to be complete by April 2025.
We are making every effort to ensure work happening in school-zones occurs mostly during school breaks. We’ll update this page with updates or new information. Thanks for your patience as we work!
Questions and comments can be sent to [email protected]
Fast Facts
- Water main replacement project
- Improves water system reliability for Hazel Dell area
- NW 99th Street from Lakeshore Ave to St. Johns